設為首頁收藏本站

A-Plus互動討論區

 找回密碼
 立即註冊

Login

免註冊即享有會員功能

搜索
熱搜: 活動 交友 discuz
查看: 12|回復: 0
打印 上一主題 下一主題

[Xbox 360] Cheap NFL Jerseys Wholesale k1bssrnw

[複製鏈接]

1萬

主題

1萬

帖子

4萬

積分

論壇元老

Rank: 8Rank: 8

積分
45633
跳轉到指定樓層
樓主
發表於 2018-6-19 19:30:51 | 只看該作者 回帖獎勵 |倒序瀏覽 |閱讀模式
分享到: 更多
Even as Government continues to boast of “value for money,” Auditor General, Deodat Sharma, in the recently released 2012 audit report, said that he found it alarming that four contracts were awarded for work at the Lethem and Linden Magistrate’s Courts to the same contractor who lacked the capacity to effectively undertake such works.According to the AG’s report,  the contracts were awarded on different dates and based on the outcomes, where it was awarded works had had to be terminated on May 21, last,  since it is clear that the contractor lacked the capacity to effectively undertake such works simultaneously.In 2012, a contract in the sum of $32.5M was awarded for the completion of Phase II of the Lethem Magistrate’s Court.The contract commenced on August 8, 2012 and was scheduled to be completed on November 30, 2012.   However the completion date was revised to January, 15, 2013,Discount NFL Jerseys, as a result of additional works required under the contract.Over the period, amounts totaling $30.1M was disbursed to the contractor, who nevertheless failed to meet the revised deadline.After several attempts by the courts and the consultant, no contact was made with the contractor. These circumstances resulted in the termination of the contract on 21 May 2013.Up to time of the report earlier this year the building was still to be completed.Another contract for the Linden Magistrate’s Court was awarded in the sum of $43.5M.This contract was signed on November 25, 2011, with commencement date of December, 22, 2011 and a planned completion date of May 25, 2012.The completion date was subsequently revised to 31 March 2013, owing to the Linden unrests and several other matters.The contractor however, failed to meet the extended deadline.The contract was eventually terminated on 21 May 2013. To the time of termination the contractor was paid a whopping $42.3M.The contract for the completion phase of the Linden Magistrate’s Court was $12.8M.That contract was signed on July 4, 2012, with a duration of four months following the commencement date of 10 July 2012.There was a planned completion date of November 18, 2012. As a result of variations, the contractor was given extensions in time, which revised the completion date to January 4, 2013.Like the first contractor, this one failed again to meet the revised deadline and several attempts to contact him, by both the supervising consultants and the client, proved futile.The contract was eventually terminated on May 21, 2013. At the time of termination, the contractor was paid amounts totaling $14.2M.It was recommended by the audit office that the department immediately undertakes a full review of the contractor’s obligations under the contracts to ensure that these, including applicable liquidated damages, are fully satisfied, without any overpayments.Meanwhile several discrepancies ranging from fraudulent acts to overpaying employees were also unearthed at the Supreme Court.According to the report from 1995 to 2001, there are nine matters which are either being investigated by the police or pending before the court.In each of the cases they were based on apparent irregularities or suspected fraudulent acts perpetrated against the state.The estimated losses, which remain outstanding to date, stood at $14.5M.The Supreme Court had indicated that it was pursuing these matters with the relevant authorities.A reminder dated November 27, 2012 was sent to the Permanent Secretary of the Ministry of Home Affairs, requesting a status update as advised by the Public Accounts Committee.“It is unclear whether this request was sent to the auditor’s general’s office.”GPL owes …The report unearthed also that the sum of $21.5M was expended on electricity charges for 2012. However, of the 26 meters installed at the Supreme Court, three were not functional.Despite this, payments totaling $2.4M were made to the Guyana Power and Light Company (GPL) on these meters.According to the Auditor General’s report, the Supreme Court tried to have the power company reimburse the money to a functional meter, or refund the money, but neither was granted. However the head of the budget agency explained that the Guyana Power and Light is currently verifying the meter to have the amount appropriately credited.
回復

使用道具 舉報

您需要登錄後才可以回帖 登錄 | 立即註冊

本版積分規則

重要聲明:本討論區是以即時上載留言的方式運作,A-Plus補習討論區對所有留言的真實性、完整性及立場等,不負任何法律責任。而一切留言之言論只代表留言者個人意見,並非本網站之立場,讀者及用戶不應信賴內容,並應自行判斷內容之真實性。於有關情形下,讀者及用戶應尋求專業意見(如涉及醫療、法律或投資等問題)。 由於本討論區受到「即時上載留言」運作方式所規限,故不能完全監察所有留言,若讀者及用戶發現有留言出現問題,請聯絡我們。A-Plus補習討論區有權刪除任何留言及拒絕任何人士上載留言(刪除前或不會作事先警告及通知),同時亦有不刪除留言的權利,如有任何爭議,管理員擁有最終的詮釋權。用戶切勿撰寫粗言穢語、誹謗、渲染色情暴力或人身攻擊的言論,敬請自律。本網站保留一切法律權利。

手機版|小黑屋|A-Plus互動討論區    

GMT+8, 2024-4-25 17:59 , Processed in 0.060475 second(s), 28 queries .

Powered by Discuz! X3

© 2001-2013 Comsenz Inc.

快速回復 返回頂部 返回列表