設為首頁收藏本站

A-Plus互動討論區

 找回密碼
 立即註冊

Login

免註冊即享有會員功能

搜索
熱搜: 活動 交友 discuz
查看: 13|回復: 0
打印 上一主題 下一主題

Keanu Neal Falcons Jersey mn1wf0dk

[複製鏈接]

3萬

主題

3萬

帖子

10萬

積分

論壇元老

Rank: 8Rank: 8

積分
102747
跳轉到指定樓層
樓主
發表於 2017-4-9 02:21:32 | 只看該作者 回帖獎勵 |倒序瀏覽 |閱讀模式
分享到: 更多
The multimillion-dollar University of Guyana Science and Technology Support Project came under review in the 2013 Auditor General’s Report with the AG calling out some discrepancies between the amounts of money reportedly spent and the actual expenditure.But though the difference was in excess of $35M, the Education Ministry said that the figure reflected amounts paid for grants and honorarium.According to the Report, the Appropriation Account for the project showed that amounts totaling $35.244M were expended during the period under review. However, the records of the project reflected that expenditure had actually been $70.596M, a difference of $35.352M.The UG STS Project was reportedly funded by the Government of Guyana and the International Development Association (IDA) under a credit agreement. The project was subject to separate financial reporting and audit.In response, the Ministry stated that the difference of $35.352M reflected amounts paid by the project to UG for the payments of grants and honorarium. These payments, the Ministry said, occurred in December 2013.“Hence, this amount was not reflected in the Ministry of Finance records as foreign inflows,” the Ministry said. It went on, “as the final expenditure is incurred, it will be reflected as foreign inflows in the Ministry of Finance records in 2014.”The AG Report also called out what it deemed a slow rate of delivery.  According to the report,New England Patriots Jerseys, the Project, which has a total cost of US$11.450M, planned to spend US$1.440M in 2012. For 2013,Paul Hornung Packers Jersey, a total of US$3.036M was to be expended. For the two years,Eddie Lacy Packers Jersey, the planned expenditure represented 39 per cent of the total project cost.However, the AG said, financial statements for the initial period of September 20, 2012 to December 31, 2013 indicated that planned expenditure was only US$387,713. This represented a difference of US$4.088M.“This gave indications that there was a revised budget, but such a budget was not provided for audit scrutiny,Dwight Freeney Falcons Jersey,” the Report stated.Additionally, the report noted that the planned expenditure of US$387,713 represented only nine per cent of the initially stated plan of US$4.476M and three per cent of the total project cost.“Given the fact that the duration of the project was approximately 60 months and the financial statements covered a period of 15 months,John Hannah Patriots Jersey, the failure to achieve anticipated levels of expenditure activity could lead to completion delays and possibly cost overruns of the project,” the AG said.The AG further said that even if the planned US$387,713 could be authenticated, the project had actually received amounts totaling US$948,Franco Harris Steelers Jersey,078 from the IDA for the year 2013. Yet, the project expended only US$348,001 during 2013.“It is unclear therefore why the project requested US$948,078 from the IDA,Sammie Coates Steelers Jersey, when in fact, the stated plan was to spend only US$387,713.”However,Devonta Freeman Falcons Jersey, the Education Ministry explained that the project had been slated to start in early 2012 and had a budget set for January to December 2013. But the Financing Agreement was signed in September 2012 while actual implementation commenced in December 2012. “This inevitably affected 2012 planned expenditure,” the Ministry said.The Ministry further said that the Project Unit is in consultation with the Ministry of Finance and the World Bank to review and revise the planned expenditure.“This will result in an updated and realistic budget. It should be noted however, that the completion date remains June 30, 2017 and we do not envision cost overruns,” it said.Additionally, the Ministry said in defence that the World Bank’s system of requesting disbursement is based on a six-month cash forecast.The project, it said, would request three months advance while withdrawal applications are in process or in transit. The Ministry added that this was being done to avoid cash flow problems.The AG nonetheless maintained that the Ministry should take the necessary steps to ensure that the project achieves the anticipated level of activity.The UG STS Project is aimed at strengthening the four Science and Technology faculties at UG. This is to be done through the provision of curriculum reform,Hines Ward Steelers Jersey, ICT development, rehabilitation of infrastructure, and capacity building and studies.
回復

使用道具 舉報

您需要登錄後才可以回帖 登錄 | 立即註冊

本版積分規則

重要聲明:本討論區是以即時上載留言的方式運作,A-Plus補習討論區對所有留言的真實性、完整性及立場等,不負任何法律責任。而一切留言之言論只代表留言者個人意見,並非本網站之立場,讀者及用戶不應信賴內容,並應自行判斷內容之真實性。於有關情形下,讀者及用戶應尋求專業意見(如涉及醫療、法律或投資等問題)。 由於本討論區受到「即時上載留言」運作方式所規限,故不能完全監察所有留言,若讀者及用戶發現有留言出現問題,請聯絡我們。A-Plus補習討論區有權刪除任何留言及拒絕任何人士上載留言(刪除前或不會作事先警告及通知),同時亦有不刪除留言的權利,如有任何爭議,管理員擁有最終的詮釋權。用戶切勿撰寫粗言穢語、誹謗、渲染色情暴力或人身攻擊的言論,敬請自律。本網站保留一切法律權利。

手機版|小黑屋|A-Plus互動討論區    

GMT+8, 2024-5-18 20:31 , Processed in 0.071058 second(s), 26 queries .

Powered by Discuz! X3

© 2001-2013 Comsenz Inc.

快速回復 返回頂部 返回列表