設為首頁收藏本站

A-Plus互動討論區

 找回密碼
 立即註冊

Login

免註冊即享有會員功能

搜索
熱搜: 活動 交友 discuz
查看: 12|回復: 0
打印 上一主題 下一主題

Artemi Panarin Jersey or technical specifications

[複製鏈接]

3萬

主題

3萬

帖子

10萬

積分

論壇元老

Rank: 8Rank: 8

積分
102747
跳轉到指定樓層
樓主
發表於 2017-7-28 03:25:46 | 只看該作者 回帖獎勵 |倒序瀏覽 |閱讀模式
分享到: 更多
Region Five administration’s acceptance of shoddy works executed by contractors consequently wasting millions in taxpayers’ money was revealed in the Auditor General’s Report 2011.The report disclosed that the Region did not properly monitor projects to see construction to specifications and in some instances certifying incomplete works as satisfactorily completed.The sum of $1.514M was expended to construct a reinforced concrete structure at Novar, East Coast Demerara. A physical check of the project showed that the culvert was poorly constructed– not aligned to the existing road and roadside drains.The report noted that no drawings or layout details for the structure was seen. In addition,NFL Jerseys Cheap, the dimensions of the structure did not conform to the specifications of the Bills of Quantities; neither did the contractor comply with the description of works. No toe piles were installed but payments were made for them.Moreover,NFL Jerseys From China, a layer of the concrete on top of the head walls can be removed by hand and the structure is unstable. The contractor was paid to remove materials from the previous structure that was demolished but that was not done.Blatant acceptance of shoddy works was also evident when the Region said that it was satisfied with the construction of a drain at No. Eight Secondary School that was incomplete. The report said that a contract totaling $3.575M was awarded to construct the drain. However, $1.716M was expended on the project.Apparently, checks made showed that the project was incomplete and no work was in progress at the site in spite of the fact that approximately eight months had already elapsed since the works were awarded to the contractor.The report revealed that a section of the drain was poorly constructed and was deemed unacceptably crooked but the Region accepted this poor quality work by certifying that the works were satisfactorily completed.Applying liquidated damages to the contractor was impossible since the contract did not have duration or a completion date. In addition, the contract documents did not include any general and special conditions of contract,Fernando Rodney Jersey, or technical specifications, despite being mentioned and referenced to in the signed contract agreement.The report also highlighted discrepancies in relation to incomplete works at the Polyclinic at Bush Lot Health Centre. The contract for the construction of the building came in 28 percent below the engineer’s estimate of $8.5M.The report stated that as of December 31, 2011, amounts totaling $2.215M were paid to the contractor but physical verification of the project revealed several discrepancies. The works were incomplete and no work was in progress at the site during the time of inspection.The contractual completion date of the project was June 8,Wholesale Authentic Jerseys, 2011,Marlon Humphrey Jersey, which had long elapsed. The contractor failed to complete works within the time frame. As such,Cheap Jerseys From China, he is liable for liquidated damages but no penalty has been instituted.
回復

使用道具 舉報

您需要登錄後才可以回帖 登錄 | 立即註冊

本版積分規則

重要聲明:本討論區是以即時上載留言的方式運作,A-Plus補習討論區對所有留言的真實性、完整性及立場等,不負任何法律責任。而一切留言之言論只代表留言者個人意見,並非本網站之立場,讀者及用戶不應信賴內容,並應自行判斷內容之真實性。於有關情形下,讀者及用戶應尋求專業意見(如涉及醫療、法律或投資等問題)。 由於本討論區受到「即時上載留言」運作方式所規限,故不能完全監察所有留言,若讀者及用戶發現有留言出現問題,請聯絡我們。A-Plus補習討論區有權刪除任何留言及拒絕任何人士上載留言(刪除前或不會作事先警告及通知),同時亦有不刪除留言的權利,如有任何爭議,管理員擁有最終的詮釋權。用戶切勿撰寫粗言穢語、誹謗、渲染色情暴力或人身攻擊的言論,敬請自律。本網站保留一切法律權利。

手機版|小黑屋|A-Plus互動討論區    

GMT+8, 2024-4-27 22:59 , Processed in 0.081335 second(s), 28 queries .

Powered by Discuz! X3

© 2001-2013 Comsenz Inc.

快速回復 返回頂部 返回列表